butt_1
butt_2
butt_3
butt_4
butt_5
butt_6
  butt_6


 

Imperial Oil Complex ‘B’ Blast Protection

·        As part of Imperial Oil’s preparation for their new Co-generation Facility the control room in Complex ‘C’ was being integrated into Complex ‘B’ and the entire building was renovated.

·        All existing services in the building were removed; however the existing control room remained operational during the entire project.

·        The mechanical scope of work included H.V.A.C., plumbing, drainage, controls, and sanitary piping.

·        We supplied and installed four custom built air handling units complete with hot water heating coils, cooling coils, humidifiers, two stages of carbon filter sections, and two stages of pre-filter sections.

·        Silencers were installed on both the supply and return ductwork for each unit.

·        The cooling was provided by a 70 ton helical rotary chiller which we supplied and installed.

·        To provide proper zone control 13 hot water re-heat coils were installed.

·        Approximately 26,000 lbs. of ductwork were estimated on this project.

·        We supplied and installed the pumps and valves included in the heat transfer packages.

 

Imperial Oil U to A Migration

·        As an additional part of the preparation for the Co-Generation Plant the control room in Complex U was moved to Complex A.

·        The existing control room in Complex A remained operational throughout the renovations.

·        9 new hot water reheat coils and 1 new electric reheat coil were installed in the new ductwork serving the first floor of the complex.

·        The existing hot water heating system was removed and all new piping was installed.

·        A new locker room was added including urinals, toilets, and showers.

 

Imperial Oil Esso Area 3 Locker Facility

·        This project involved providing Mechanical and H.V.A.C. systems for a new locker facility.

·        We were required to supply and install 4 large hot water heaters to serve the new locker area.

·        We also supplied and installed all of the shower and washroom fixtures.

·        The building was heated and cooled by three split systems.

·        In order to meet the fresh air requirements for offices a stand alone ERV unit was installed.

·        The washrooms and lockers also required three exhaust fans.

 

Imperial Oil Research Building H.V.A.C. Upgrade

·        Over the course of several projects the entire building H.V.A.C. system was upgraded.

·        The existing air handling equipment the bulk of which was in the basement mechanical room had to be demolished.

·        The equipment had to be dismantled into pieces in order to be removed from the building.

·        The new custom built air handlers had to be assembled inside the mechanical room.

·        We supplied and piped new Chillers for the air conditioning of the building.

·        Several of the spaces that were modified were laboratories.  We installed stainless steel fume exhaust ductwork, new fume hoods, new fume arms, and some new dust collectors.

·        New wall fin radiation heat was required as well as new ductwork.